The Georgia
Department of Transportation has decided to chip in $200,000 toward the
construction of the cart path bridge to span the CSX railroad tracks and
connect the West Village area to the rest of Peachtree City.
The bridge,
projected to cost between $600,000 and $800,000, will have to wait, though.
Since the DOT funding won't be available until June of 2002, the city
will wait until then to solicit bids for the project, said City Planner
David Rast.
The bridge
will hook up to the path behind the Marketplace retail center, and it
will cross over to Line Creek Baptist Church, Rast said. From there the
path will extend to the future Wal-Mart and Home Depot stores, he said.
RAM Development has agreed to put the paths in place for Wal-Mart and
Home Depot, Rast added.
The city is
asking the DOT whether it could be feasible to locate the bridge near
the Ga. Highway 54 roadway bridge. That way, the city could use the DOT's
right-of-way without worrying about securing additional right-of-way from
the railroad.
But much of
that concept depends on how long it might take for the state to widen
that bridge when Hwy. 54 is eventually expanded to four lanes, Rast said.
The timing
of the highway widening also hinges on another cart path project involving
the bridge: tunneling the cart path system under the highway to create
a "cloverleaf" approach to the bridge. Such a design would allow
residents from Planterra Ridge subdivision to travel under Hwy. 54, access
the bridge, cross the railroad tracks and then head south under another
tunnel to reach The Avenue at Peachtree City retail center, which is currently
under construction.
The "cloverleaf"
design is so named because it will use loops to bring the path from the
lower level of the tunnel up to the bridge, which will be much higher
in elevation.
"It's
a rather innovative solution," Rast said.
Cousins Properties,
the developer of The Avenue project, has also agreed to connect the center
to the cart path also, Rast said.
The DOT may
also help fund the project to tunnel under the highway, Rast said.
The city had
originally requested $300,000 in DOT funds for the bridge, but the number
was cut because there were so many other projects that were funded, Rast
said. The city already has $250,000 in impact fees designated for the
bridge, he added.