The contract
between Coweta County and Atlanta also calls for up to 15 million gallons
of drinking water per day within five years based on improvements to the
Atlanta Water System.
"It is
a milestone day for the water department," commented Water Department
head Harry Hughes in the press release. "The next milestone will
be when the water lines are connected."
The water being
purchased from the city of Atlanta will be priced at approximately 90
cents per thousand gallons under an agreed rebate program, which is designed
to offer reduced water rates to Coweta County as a means to repay the
county for the cost of needed water lines outside the county's borders.
After the rebate,
the water price is set to be $1.25 per thousand gallons. Newnan Utilities,
currently the sole provider of water to the county system, charges $1.45
per thousand gallons.
"Coweta
County has acted quickly to provide a supplemental supplier of water to
serve our residents," Coweta County Commission Chairman Robert Wood
said in the press release. "We were given a deadline to provide supplemental
water and we have met that deadline, assuring a more adequate water supply
for everyone."
Coweta County's
water system currently uses an average of five million gallons of water
per day and peaked at approximately nine million gallons during 2000.
To continue
the project on a "fast track," the commissioners approved contractors
Tuesday night to begin installation of needed water lines.
There will
be two connections to the Atlanta system, one on the east side and one
on the west side of the county. Mid-South Builders of Lithonia was low
bidder on the west side connection at $1.8 million. Ronny D. Jones Enterprises
Inc. of Newnan was low bidder on the east side connection at $2.5 million.
The county
is working toward a completion date of May 1.
While the contract
with the city of Atlanta provides an immediate boost to the county's available
water supply, it is by no means the only avenue being worked on by the
Board of Commissioners to provide additional water for the county's system,
according to the county news release.
Also in hand
is a contract with the city of Griffin to provide up to 10 million gallons
of water per day incrementally beginning in 2004-2005, based on completion
of new treatment and storage facilities, the release states.
Work also is
progressing on a treatment facility at the B.T. Brown Reservoir in northwestern
Coweta County that will provide between six and eight million gallons
per day. Completion is scheduled for the end of 2003.