At its meeting
Wednesday night, Peachtree City's Water and Sewer Authority will likely
approve a contract for engineering work to replace three pump stations
in town.
The authority
has already approved a $584,350 construction contract for the pump stations
at the following locations: one by Lake Peachtree, one behind the Publix
shopping center and one off Stratford Court. The winning bid came from
Willow Construction, Inc. which was the lowest bidder and has also performed
work for the city before, said WASA General Manager Larry Turner.
Construction
of the pump stations will take approximately nine months according to
estimates.
The only other
item on WASA's agenda is the election of officers, which occurs annually.
WASA's officers include a chairman, vice-chairman and a secretary-treasurer.