An effort
to stop a large utility marketer from building a plant in
neighboring Heard County appears to be running out of
steam.
Commissioner
Jim McGuffey told the Coweta Board of Commissioners
Tuesday afternoon that it appears there is nothing the
county can do to stop Dynegy from building a 500-megawatt
power station just across the line in Heard County.
But
McGuffey said the news is not all bad.
After
meeting with company officials last week, McGuffey said
the company appears to be willing to work with concerned
Coweta residents.
The company
plans to meet with residents in early April and address
many of their specific concerns. McGuffey said two of his
main concerns were the sound and the smell that could be
generated from the natural gas plant.
But
officials said those two issues are not a problem and
they would be willing to work with Coweta officials to
get the word out on the plant's operations.
McGuffey
said the company is planning not to use the six acres of
the property that spills into Coweta County and has
pledged to plant the area with pines to serve as a
buffer.
He also
said that no construction vehicles would be allowed on
Hawk or Midway roads and the county would monitor the
situation.
If we do
see construction vehicles, we told them that we would put
up barricades and they did not have a problem with that,
he said.
Company
officials were very apologetic for not better informing
Coweta residents, he added, and said he thought the
company would come under the state's guidelines for
developments of regional impact, but found out different.
The state
says we're a metro county and Heard is not, so they did
not have to get our input, he said.
He pledged
to keep the commission up to date on the situation.