While Home
Depot's site plans for a 137,184-sq. ft. store failed to
pass muster by the Peachtree City Planning Commission
Monday night, the debate over building a "big
box" retail outlet in the city is just beginning.
The
commission voted 4-1 Monday night to deny approval of
project's site plans which cover 21.66 acres of the total
parcel of 42.3 acres acres off Ga. Highway 54, despite
city staff recommendations to the contrary. It was
originally presented to the Planning Commission Oct. 11
and tabled.
In an
overview of the project to the commission, city planner
David Rast said, "The revised site plan responds to
citys staff's suggestions and meets or exceeds all of the
requirements and guidelines found within the city's land
development ordinance."
The
designated property is zoned general commercial (GC), a
category that would allow a Home Depot store. It is on
the property owned by the Huddleston family, just west of
the railroad bridge on Hwy. 54.
Key to
making the retail center a reality is inclusion of a
number of road improvements which must be built, or paid
for by the developer. These upgrades are necessary to
bring the project into compliance with the city's newly
adopted traffic impact ordinance. An added condition
states that the developer also must provide documentation
from the Georgia Department of Transportation approving
the highway modifications.
These
improvements include retiming the traffic signal at the
intersection of Ga. highways 54 and 74, prohibiting left
turns onto Huddleston Road from the west bound lanes on
Hwy. 54., and adding a signal at the entrance of the
store across from Planterra Ridge.
The
increased traffic load on the city's already crowded main
arteries is the factor that concerned most citizens
attending Monday night's meeting. Also, business owners
along Huddleston Road were riled by the "no turn off
Hwy. 54" proposal.
Jim
Schultz, who owns Peachtree City Kennels on Fulton Court
directly off Huddleston Road, claimed the city was doing
"everything to accommodate Home Depot" and
sacrificing established businesses along Huddleston Road.
John
Proffitt said there are 47 commercial businesses and 37
industrial businesses that would be affected if the left
turn lane onto Huddleston from Hwy. 54 were eliminated.
He predicted the change would be a "sure
killer" for Huddleston Road businesses. "You
might as well write those businesses off."
The traffic
plan presented by Ed Ellis and prepared by Dames and
Moore, a firm retained by Peachtree City to provide
criteria for judging new developments, was poorly
received by the audience. In a power point presentation,
Ellis showed how cars, depicted by tiny moving dots,
would flow through the 54/74 intersection smoothly, even
at peak afternoon rush hours.
The site
plans will likely be appealed before city council and the
project developers, Ram Development Group, have also
retained the law firm of Dillard and Galloway to
represent them. Present Monday night was attorney Andrea
Jones. "There is no legal justification not to make
a decision tonight," she told the commission.
"Any denial of the application would be
unconstitutional," she said.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…