The Starr's
Mill High School stadium, now under construction, will
have concrete bleachers instead of aluminum seating,
based on a funding arrangement with the Panther Athletic
Booster Club.
The
boosters have agreed to raise $150,000, half of the
$300,000 necessary to have concrete in place of aluminum,
which is in short supply worldwide according to Wayne
Leslie of Leslie Contracting Inc.
"There
will no incremental costs to the Board of
Education," Jimmy McCullough, president of the PABC,
told the Fayette County Board of Education Thursday. The
other $150,000 has been pledged by the Fayette Community
Foundation, a group of anonymous donors.
Leslie has
issued the PABC a two-year, interest-free note on the
$150,000 and McCullough is confident his organization can
muster the money. Their current budget is in excess of
$100,000 and the move to switch to conrete has the full
support of the PABC and the Starr's Mill Band Boosters.
Completion
of the stadium is likely to be in February 2000. The
uncertainty of obtaining the aluminum bleachers could
have delayed the project even further. "This could
have a severe impact on the spring athletic programs, as
well as the inaugural graduation exercise,"
McCullough said.
The board
called the proposal a win-win arrangement and gave
approval of the plan, pending the legal consent of their
attorney.







Easy button Return it to long suffering taxpayers including those who have paid huge tabs to educate other people's kids…