PTC Council eyes lake expenses

0
19

Those expecting to hear the next proposal by Great Wolf Family Lodge at the March 5 meeting of the Peachtree City Council may be disappointed. The company is requesting that the agenda item be continued until March 19.

Great Wolf last week asked that the rezoning for the establishment of a family-oriented hotel and indoor water park at the current site of the Dolce Atlanta-Peachtree Hotel and Resort be continued to the March 19 council meeting. The council will consider the request on March 5.

Another item that may be ready for the meeting concerns information on expenses for the Lake Peachtree dam and spillway project.

Massana Construction, by virtue of its contract with Fayette County, has preparations underway to begin the lake dredging work. A portion of the county project will also include temporary spillway work.

Both the dredging and spillway work are expected to be completed in June.

Also at the March 5 meeting, Public Service Director John Rorie will present an update on the status of the Facility Authority bond projects.

The council will also consider a recommendation to approve a fee schedule for payments of stormwater bills, businesses licenses and building permits.